PMI Professional in Business Analysis (PMI-PBA) certification is a hot Business Analysis(BA) certification. Business analysis has become a competency of critical importance to project management. Becoming certified as a business analysis (BA) expert can move your career in a fresh direction while opportunities for BAs are on the rise. To help you be a BA certified, DumpsBase has released new PMI-PBA dumps online to ensure that you can pass PMI Professional in Business Analysis (PMI-PBA) exam successfully. 

Check PMI Business Analysis Certification PMI-PBA Free Dumps

1. The project team is working on the requirements specifications for a new product. The team reached a decision on which requirements will be included in the next release A third of the stakeholders endorse one approach while no other approach achieved more than a quarter of the vote.

Which decision role was used?

2. The business analyst has been assigned to a project involving a low number of stakeholders.

Which technique should be used to elicit requirements?

3. A major stakeholder wants to know how the implementation of new features in the development of a product is progressing.

Which of the following should be reported to the stakeholder?

4. The technology department identified a defect in the company's software, which leads to an increase in human resource requirements to perform manual transactions as a workaround for tasks that should have been automated. The company begins losing money, so it hires a business analyst to produce a business case that outlines the problem/opportunity, potential options, and a recommendation for how to proceed.

Which of the following analyses must the business analyst perform in order to complete the business case and arrive at a solid recommendation"?

5. A business analyst has elicited, documented, and verified the requirements, discovering that there are not enough resources to deliver all the requirements.

Which technique should the business analyst

employ to rectify the issue?

6. The stakeholders for a newly approved project are subject matter experts who are very knowledgeable in the client's business and will provide the project requirements. The project team scheduled separate sessions with each subject matter expert to identify and prioritize the requirements.

Which technique is being used?

7. A business analyst is assigned to the lead analyst role for a project. This project is one of the largest in the history of the company and includes several components and complex interfaces. The system in development will be used by a wide variety of stakeholders.

Which tool should the business analyst use to trace the large number of requirements that will be generated by this project?

8. The client produced a specification for a new product to be developed by Company A. Company A designed and successfully tested the new product against the test plan. yet the client does not agree that it meets the specification.

What could have caused this?

9. During validation of a project solution, the business analyst discovers that a requirement has been altered. Instead of placing the company logo in the upper-left corner of the window, it is displayed in the upper-right corner. When the business analyst asks the developer about the change, the developer says that one of the stakeholders asked directly for the change.

Which corrective action should the business analyst take?

10. Last year, a company registered a high number of complaints about its customer service.

Which of the following tools or lechniques can help to identify the high-priority changes needed to improve that service?

11. Which document best provides the boundaries for product development?

12. During the project execution phase, the client requests the addition of a new feature.

Which of the following would allow the business analyst to determine the impact for the specific requirement change?

13. Which statement accurately depicts what changes can be made to requirements after they are baselined?

14. A business analysl is working on a project to implement a new call management system for a help desk. They expected the average time interval to answer a call to decrease over time, but the interval has increased instead.

Which technique should the business analyst use to investigate the problem?

15. What are some of the components of a requirements management plan?

16. A business analyst is preparing a requirements management plan and needs to define a method to deal with a complex project with stakeholders who find it difficult to articulate their needs.

Which method would best minimize requirements risk?

17. The business analyst is conducting a feasibility study to understand how well a potential solution fits into the organization.

What kind of feasibility assessment is the business analyst undertaking?

18. A project team has been assembled to reduce production costs. The business analyst is working with the project team to review and approve requirements. A stakeholder from the assembly line area has an issue with one of the requirements since it is dependent on using existing equipment that is set to be retired within the next six months.

Which of these techniques would the business analyst use to manage issues identified by stakeholders with requirements to ensure that those issues are resolved?

19. A business analyst is attempting to elicit requirements on a current project. The business subject matter experts (SMEs) from various departments in the company question how the solution will work with their various systems.

Which modeling technique should the business analyst use to depict how the solution will work with all of the company's systems?

20. After conducting a brainstorming session with a group of project participants, the business analyst feels that the elicited requirements are biased.

Which tool or technique could be used to gain an objective, first-hand insight into tasks and activities that are difficult to describe?

21. Which of the following techniques is used to identify ambiguous or unverifiable requirements?

22. A business analyst captures an application's current limitations and consults with end users to identify new features for the next version.

What can be used to analyze this information and determine project scope?

23. A company has just finished the development work for a new software sales tracking application and is in the process of validating that the new application meets all of the acceptance criteria defined for the business requirements. During the validation process, a stakeholder discovers that the application does not provide the selection criteria needed to produce the sales volume reporting required by the company's financial department. The business analyst for the project determines that the selection criteria needed was not specified in the system requirements or design specifications.

Which of the following tools and/or techniques might be used by the business analyst to determine how the selection criteria requirement was missed?

24. The business analyst wishes lo clarify the project's key business drivers and ensure that requirements can be prioritized to provide maximum business value.

Which question should the business analyst ask of stakeholders to help obtain this clarification?

25. A stakeholder requests to add new critical requirements the day before the scheduled baseline requirements approval meeting. The stakeholder insists that these requirements must be taken into account despite time and budget constraints.

What is the most effective way to manage this situation?

26. How can a SWOT analysis help when deciding between several possible options to address a business problem?

27. Company A has initialed a project to update their online ordering system. The business analyst has noticed that the purchasing department, a primary stakeholder. is excluded from the list of stakeholders.

In which reference matenal can the business analyst find information about the missing project stakeholders?

28. Which of the following best describes the function of the requirements baseline?

29. Once a new project has been identified, the business analyst works with project team members to define what will be included in and excluded from the new system.

Which of the following has the business analyst defined?

30. A project affects Ihe marketing unit and procurement unit. The project manager gives the business analyst an overview of the project for the first time.

What should the business analyst do immediately after the discussion?

31. A business analyst is ready lo begin requirements elicitation; however, stakeholders are not available to participate for another two weeks.

Which elicitation technique should the business analyst use during this time?

32. A business analyst is working on a highly complex project and has elicited a large number of requirements from stakeholders in several departments Due to the large number of requirements, the stakeholders have determined that they would like to prioritize them to minimize a potentially large scope.

Which technique could the business analyst use to manage requirements?

33. A business analyst created requirements for production of a product extract file for several systems. After reviewing the complex systems and dividing the processes into manageable tasks, the business

analyst is able to identify the tasks required to implement the deliverable.

Which analysis technique has the business analyst used?

34. Company A has set aside capital to invest in an upgrade to their scheduling system Documentation of the current structure was presented to the business analyst However, the description of certain steps are not documented clearly, and the business analyst has not been allowed to inspect the existing system. During elicitation. the business analyst asked questions of the schedulers as they performed functions in order to gain an understanding of the process.

Which type of elicitation technique did the business analyst use in this instance?

35. During the initial phase of a project, which technique could assist in identifying and categorizing the stakeholders?

36. A business analyst has incorporated all the relevant feedback from stakeholders in the business analysis plan.

Which next step should the business analyst take?

37. After implementation of the product, the customer reports defects.

What is the best course of action to take?

38. Change control systems include provisions to implement changes without formal review in the event of an emergency. When this provision is utilized:

39. A company is working on implementing a software application. They are converting their complex, m-house processes into the new system. The business analyst has been asked to analyze the processes.

Which technique should be followed?

40. A startup company sells organic vegetable and fruit smoothies. Management is tracking a rapid decrease in sales of their best-selling juice, so they contract a business analyst to identify solutions in order to increase sales by comparing similar products offered by competitors.

Which technique or tool should be used?

41. A business analyst is leading a project to implement automated order entry software at a local pizza restaurant. The business analyst has very little information about the project the ordering process takes too long and often ends in incorrect orders.

What step should the business analyst take next?

42. The business analyst has completed the requirements gathering and documentation processes in developing a baseline document. Several signoffs are needed During the joint review process with the key stakeholders, the stakeholders announce that they are still not ready to sign off due to a communication gap.

Which technique should the business analyst have followed to ensure consensus?

43. The business analyst is seriously concerned about the possibility of differing interpretations of data items mentioned in the requirements documents.

Which course of action should the business analyst take to minimize the risk of misunderstanding?

44. A business analyst in organization Y is assigned to elicit requirements in a project within a defined timeline. The business analyst has identified and invited key stakeholders to a requirements workshop.

However, the stakeholders are not giving clear and concise requirements; their opinions about requirements are changing and conflicting with each other in the meeting. In the end. the business analyst could not elicit and define the requirements and therefore adjourned the meeting.

Which tool or technique could have been used by business analyst to avoid this situation?

45. A project team has 120 days to deliver a solution, but the stakeholders have too many requirements for the delivery window.

What requirements prioritization technique should be used to determine which requirements will be delivered?

46. Inthe middle of a project, a new requirement was added to the scope. The business analyst must determine if any impacts, dependencies, or risks are associated with the addition to the scope.

What task should the business analyst perform in order to identify these impacts?

47. A system enhancement project has been initiated to address the concerns of an external group of stakeholders not included in the first release.

What should be done to ensure stakeholder satisfaction with the enhancement?

48. During user acceptance testing, a defect is logged by a user from a department that did not participate in the requirements analysis.

To avoid this situation and minimize impact on the project, the user should have been:

49. A business analyst is working on a system enhancement project and has completed the requirements according to the requirements management plan. The business analyst is now ready to request approval from the stakeholders.

How should the business analyst obtain approval?

50. When a change request is received, the business analyst is responsible for:


 

Portfolio Management Professional (PfMP) Certified PfMP Exam Dumps
Project Management Professional PMP Updated Exam Dumps

Add a Comment

Your email address will not be published. Required fields are marked *