Taking the AACE Planning & Scheduling Professional (PSP) Exam (AACE-PSP) exam was always challenging, but with DumpsBase, you can succeed now. DumpsBase understands that taking the AACE-PSP exam is important to level up your credentials and achieve your career goals. We have updated the AACE-PSP dumps to V9.02 with 77 practice questions and answers so that you can prepare for your AACE-PSP Planning & Scheduling Professional (PSP) Exam without changing your busy routine. Prepare confidently using DumpsBase’s AACE-PSP exam dumps, paving the way for your success. All these actual AACE International AACE-PSP exam questions and answers are taken from the real AACE-PSP exam topics after thorough research by the experts. The experts have also verified the AACE-PSP questions to ensure the validity of the AACE-PSP exam dumps (V9.02). Start with DumpsBase, we promise you that you will pass your AACE-PSP Planning & Scheduling Professional (PSP) Exam with the help of AACE-PSP dumps (V9.02) in one go.

Below are the AACE-PSP free dumps to help you check the updated dumps:

1. Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?

2. Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.

3. In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):

4. Which of the following is NOT required when initially planning a project?

5. Which of the following is NOT a tool or technique used to perform scope planning?

6. Which of the following are NOT considerations or constraints of the planning process for construction scheduling?

7. What method offers the best chance of the schedule being used effectively to implement the project in the field?

8. At a minimum, periodic reporting must be done at what interval?

9. Which is NOT an industry-recognized methodology for quantifying critical delay?

10. What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?

11. Time-scaled logic diagrams are

12. Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT

13. You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company's board of directors for its consideration.

What document or resource is likely to be MOST valuable in determining the schedule's work activity durations?

14. Free float is the

15. What is a key first step in developing a critical path method schedule?

16. Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that

17. A driving relationship is _____________________.

18. If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using

19. An early start constraint dictates

20. Constraints control events or activities that __________________.

21. Which of the following is NOT required when performing weekly or monthly schedule updates?

22. Which of the following will always describe the critical path? The path with

23. Of the following update procedures, which is the least important in achieving an accurate forecast for completion of a construction schedule?

24. What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?

25. An earned value-based project control system can use either of which two budgets as the basis of its